Changes between Version 7 and Version 8 of SprintPlanning20110503


Ignore:
Timestamp:
May 4, 2011, 1:01:07 PM (7 years ago)
Author:
stephen
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • SprintPlanning20110503

    v7 v8  
    6565  https://lists.isc.org/pipermail/bind10-dev/2011-May/002229.html
    6666
    67 Jinmei: Only completed some of the tasks. Only completed signing - need to complete verify.  Need to add TSIG to b10-auth (not originally planned).  Suggest that we defer #856 (add ability to send TSIG query to src/bin/host) as this was added as a user-visible feature but we don't release "host".
     67Jinmei: Only completed some of the tasks. Only completed signing - need to complete verify.  Need to add TSIG to b10-auth (#875, not originally planned).  Suggest that we defer #856 (add ability to send TSIG query to src/bin/host) as this was added as a user-visible feature but we don't release "host".
    6868
    6969Jinmei: A number of things are awaiting review and many thing depend on it (so do reviews).  May be able to parallelise - do part of #815 (xfrin) if we assume that #814 (currently in review) is OK. 
     
    220220
    221221* Jerry: Reset task #856 to "!UnAssigned" and move to general task backlog (i.e. no milestone associated with it). ''(Done)''
     222* Stephen: Add task #875 (b10-auth needs to be able to handle TSIG) to current sprint.  ''(Done)''
    222223* Stephen: Add task to implement logging with log4cplus (to be done on the next sprint). ''(Done: #899)''
    223224* Stephen: Add task to current sprint to check that log4cplus builds on all build-bot systems. ''(Done: #898)''